120kW
System Capacity
168,000
kWh Annual Yield
42%
Energy Bill Reduction
6.8 yrs
Payback Period
Project Overview
A Williams Landing logistics and warehousing company approached CMD Vertex Engineering seeking to reduce their significant daytime electricity costs. Operating Monday to Saturday with peak loads between 7am and 5pm, the facility was an ideal candidate for a large-scale rooftop solar system.
CMD Vertex Engineering was engaged to provide full engineering consultation — from initial feasibility and system design through to DNSP grid connection approval and contractor tender support.
Challenges
Our Solutions
Project Outcomes
"CMD Vertex handled everything from the structural assessment to the DNSP approval. We had zero surprises on site and the system was commissioned on schedule. The savings have exceeded our projections."
Operations Manager — Williams Landing Logistics Facility